Chandler and Main Street Utility Improvements

Project Map

This project includes but is not limited to replacement of 2,600 feet of potable water pipeline at S. Chandler Ave. and Main St.  The existing pipeline has exceeded its useful lifespan. Project involves replacing the failing 14 inch cast iron water mainline with 24 inch PVC water main. Paving and fire hydrants will be replaced within the projects area.

Timeline: Construction began December 2023 and is estimated to be completed April 2024. 

Goal: Improved services for existing customers and additional capacity for future customers.  This project will provide construction water support for Preston Harbor Development.

Contractor: SYB Construction