Lake Texoma Raw Water Pump Station and Transmission Line

This project includes the installation of a new intake structure on Lake Texoma capable of handling up to 50 million gallons daily at full build out. It also includes a new 42" raw water transmission line that will transport raw water from the pump station to Lake Randell, where it will then enter the treatment plant. New fiber optic line will be laid to connect the pump station to the City's SCADA network. Improvements and additions to the treated water system in the areas adjacent to the pump station and transmission line, including a new meter and vault for Eisenhower State Park are also included. 

Timeline: Construction began January 2023 and is scheduled to be completed in late 2025.

Goal: Construct of a new station that will meet the community's water demands and include scalability to grow in line with development. .

Contractor: Archer Western Construction